Starting in February 2021, after a concentrated construction period with a high sense of responsibility of Ecoba ENT contractor’s engineers, clean water treatment plant in Nam Son – Hap Linh Industrial Park, with a capacity of 19,000 m3/day has been gradually completed and is expected to be handed over at the end of September 2021.
Nam Son – Hap Linh Industrial Park is invested by Kinh Bac Urban Development Corporation (KBC) with the orientation of developing concentrated industrial zones, receiving industrial production lines that do not pollute the environment.
Clean water treatment plant in Nam Son – Hap Linh Industrial Park was entrusted by KBC investor to hand over to Ecoba Environmental Technology Co., Ltd (Ecoba ENT) as the main contractor. Previously, Ecoba ENT has also cooperated with KBC in a number of maintenance and upgrading projects for wastewater treatment plants and water supply plants in Que Vo Industrial Park, Bac Ninh, the contractor’s capacity has also been demonstrated and demonstrated. investors trust.
Clean water treatment plant in Nam Son – Hap Linh Industrial Park
Commencement during the time of the Covid-19 epidemic has complicated developments, greatly affecting human resources, material transportation as well as construction, but the contractor Ecoba ENT always tries to optimize the resources well, ensure the construction progress and safety for the clean water treatment plant of Nam Son – Hap Linh Industrial Park with the goal of completing the proposed work items according to the schedule, quality, aesthetics and safety safe.
After more than 6 months of construction, the clean water treatment plant in Nam Son – Hap Linh Industrial Park has gradually taken shape and is entering the finishing stage. By the end of September 2021, the contractor Ecoba ENT will conduct static acceptance of the installed equipment at the site. This is a step to check and determine whether the quality of the installation is correct with the design and in accordance with the technical requirements of the installation or not, in order to prepare the equipment for the no-load test run.
By the end of September 2021, the contractor Ecoba ENT will conduct static acceptance of the installed equipment at the site
In addition, the works to ensure traffic and environmental sanitation are also seriously implemented by the Ecoba ENT contractor during the construction process, in order to keep the surrounding area clean without affecting traffic and the environment of Nam Son – Hap Linh Industrial Park.
Some pictures of Clean water treatment plant in Nam Son – Hap Linh Industrial Park: